Rule of Credit
Previous Topic  Next Topic 

While stringent monitoring of the milestone tasks is necessary for the timely completion of the project, the project manager needs to be informed of any delay in the Project well in advance so that appropriate preventive measures can be taken. The important milestone stages related to the progress in the deliverables are mentioned in the Rule of Credit module.

In the usual engineering scenario, the tasks in WBS are delivered to the client several times for review and approval. The progress of the tasks is constantly monitored through reports with the help of the Rule of Credit. The Rule of Credit provides the Planned and Actual dates for intermediate stages in the work flow. 

User may select the appropriate issue purpose, approval status codes and internal status codes for the various work flow stages while creating rule of credit. By linking the issue purpose, approval status codes and internal status codes to the rules of credit actual dates for multiple issues to the client can be monitored.

Creating a rule set

Rule set can be defined for a group of tasks, documents, etc. for which the same rule of credits are to be monitored.

For Example: A rule set called Design Milestones can be defined, which can be set for a group of designing tasks in the genealogy.

To create a rule set

Creating Rules of Credit

For the Rule set defined we can create rules of credit based on which the progress of deliverables related to the project is monitored.

To create rule of credit

Assigning permission to update actual finish dates

When rulesets are inherited to tasks from the project, certain rules (milestones) may have approvals from customer and actual finish date of such rule’s  may need to be updated only by people with special privileges; while the ‘Actual Finish Date’ for the rest of the rules may be updated by anyone with rights to carry out the operation. Permission to edit  Actual Finish Date of the rule can be assigned to selected user groups.

To select user groups

Editing a rule / rule set

A rule or rule set can be edited.

To edit rule/rule set

Deleting a rule/rule set

Select a rule/rule set and click Remove to delete the rule/rule set from the project.

Importing rule of credit

Import of rule of credit helps in reusing of rules of credit data from similar projects. The project from which the rules of credit values are imported is defined as the Source project. The project to which the values are imported is defined as the Destination project. Rule of Credit can be imported from a Project or an MS Excel sheet.

Importing rule of credit from a project

Rule of credit can be imported from another project.

To import rule of credit from project

Creating rule of credit in bulk

Rule of credit can be generated in bulk.

To bulk create rule of credit

Refreshing WBS

Once changes are made in Rule of Credit,  changes have to be reflected in the WBS.

To refresh WBS