Budget
Previous Topic  Next Topic 

The project budget is a detailed estimate of money required to complete a project.

NOTE: The ‘Budget’ tab will be visible only for users who have View Budget permission configured in Modular Security or in Project.

To view the budget details

Creating Budget Line Items

Line items are the individual budget information, that are grouped based on the cost code to give the total Budget. Once a line item is created successfully, its hierarchical structure will be added to the budget.

To create budget line items

Updating or Editing Line Items

A line item can be edited or the values can be updated.

To edit/update line items


Removing line items

It is possible to remove a line item that is already created. On removing a line item,  total budget values will be recalculated.

To remove line items

Viewing Line Item list

The list of line items can be viewed without any hierarchy. Line Items can be grouped based on different properties.

To view line item list

Updating Spent

In Cost module, there is a facility to release payments against commitments (PO). In certain industry scenarios, payments are required to be made without reference to commitments. For Example: Travel reimbursements etc., which will not have any commitments.

Hence facility to update ‘Spent’ without referring to commitments is provided.

To update spent

  1. On the menu click Update Sent.

Update Spent Information window is displayed.

Figure: Update Spent Information window

On the window enter values for the following fields.

COST CODE: Value is displayed by default. Click the browse button to select a different CODE.

LINE ITEM NO: Value is displayed by default. Click the browse button to select a different value.

LINE ITEM DESCRIPTION: Values based on the selected line item is displayed here.

COMMITMENT: Click the browse button to select a commitment.

PAYMENT DESCRIPTION: Value is displayed by default.

SPENT DATE: Select the spent date from a drop-down list.

SPENT AMOUNT: Enter the spent amount.

  1. Click Add Item to create a spent against the line item. 

On successfully validation, the item will be added to the grid in the bottom half of the window. Sum of the added items is displayed at the lower part of the window.

  1. Click SaveSpent Updated Successfully message is displayed.

Viewing Spent Details

Spent details  can be viewed for items with spent.

To view spent details

  1. Select an item and in the menu click Spent Details. Spent Details window is displayed.

Figure: Spent Details window

If the selected line item does not have any spent, an alert message, Selected line item does not have any direct cost is displayed.

On the window click New to create a direct cost, click Update to edit the existing cost.

Changing views

Different layouts can be selected for displaying the budget details. Layouts available are Basic and Advanced

On selecting the layout as Basic, the following window is displayed. Here basic details of the line item is displayed.

Figure: Basic Layout

On selecting the layout as Advanced, the following window is displayed. Here detailed information of the line item is displayed.


Figure: Advanced Layout

Distributing Budgets

Budgets allocated may be spent over a particular time interval. Therefore, these budget amounts have to be distributed across defined time interval. Budgets can be distributed using either manual or automatic distribution. Automatic distribution is made possible using Beta distribution. Option to distribute line items will be available in  the Line Item Details window.

To distribute line items

Distributing budgets manually

In some cases budgets are distributed manually.

To distribute budget manually

Viewing distribution details


Distribution details of a line item can be viewed from Line Item Details window.


To view distribution details

Creating and viewing cost baselines

Baselines are copies of existing cost details. A baseline is created for future reference. This can be done at any point of time. Created baselines can be viewed and multiple baselines can be compared.

To create a baseline


To view baseline history

Comparing baselines

There may exist more than one baselines in Projects. User may compare any two baselines to understand the changes between them; as well as user may compare any of the existing baseline with the current budget.

To compare baselines

Importing/Exporting Budget Line Items

Budget line items can be imported in bulk. Further line items can be exported to an MS Excel file, values can be edited and the edited details can be updated back to the system. An MS Excel template is used as the medium for generating a template. Following operations can be carried out from the Line Item Import/Export menu.

Figure: Import/Export Menu

Generate Template

Import

Export

Update

Bulk Operations Log

First step in carrying out an Import operation is generating an MS Excel template.

Generating  MS Excel Template

MS Excel template is used as the medium for importing budget line items.

To generate a template

Importing line item details

Line item details entered in the excel template is imported to the system.

To import line item details

Exporting line items

Existing list of budget line items can be exported to an MS Excel template.

To export line items

Updating line item details

After exporting the budget line items using the export option, desired changes can be made in the exported line items in the MS Excel file. The changed values can be updated in the system.

To update changed line item values

Operation Log

Bulk operations carried out and the status  of the operations can be viewed from the bulk operations log.

To open operations log window