Cost Changes
Previous Topic  Next Topic 

Change Orders and Change requests are created inside a Project against Budget,  Commitments or Receivables to mark changes.

Change Order: Change Order typically represent an underlying change in scope or unanticipated cost that has occurred on the project. As a result, change orders will always result in a modification to the project budget. They can be initiated by an external request – such as an RFI from a customer or other stakeholder – or they can originate from an internal source, design change, or as needed to rectify n error. Change order may be created for Budgets and the Commitments in a Project.

Change Request: Typically, a user may create a change order to flag a change in Budget or Commitment. However, change orders cannot be created by all project resources, but only by the specific resources having relevant permission. Nevertheless, any resource in a Project may flag change by creating a change request for Budget or Commitments, which upon the approval of the concerned authority will be added to a change order.

Operations related to Change Order and Change Request are carried out from the Cost Changes tab.

  1. Click Cost Changes tab. Cost Changes window is displayed. 

Two hyperlinks Change Order and Change Request is displayed here. By default hyperlink Change Order is selected. All the change orders created with its details are displayed here.

Figure: Cost Changes window

Handling Change Orders

Change Orders can be created for Commitments and Budgets.

Creating and managing Budget Change Orders

Change orders can be created for Budget, created change orders can be edited and if need arise created change order can be removed.

To create a budget change order

Fetching approved change requests

Budget Change orders can be created from approved Budget Change requests.

To create change orders from change requests

Updating budget change order

A created change order can be edited.

To edit budget change order

Removing  budget change orders

Changes Orders can be removed.

To remove change orders

Creating and managing commitment change orders

Change orders can be created for Commitments, created change orders can be edited and if need arise created change order can be removed.

To create change order for commitments

Handling Change Requests

Typically, a user may create a change order to flag a change in Budget or Commitment. However, change orders cannot be created by all project resources, but only by the specific resources having relevant permission. Nevertheless, any resource in a Project may flag change by creating a change request for Budget or Commitments, which upon the approval of the concerned authority will be added to a change order. 

To open change request window

Creating Budget Change Request

Budget change requests can be created, values can be updated later and the change request can be removed if it is not required.

To create a budget change request

Updating budget change request

A created change request can be edited.

To edit budget change request

Removing budget change request

Changes Requests can be removed.

To remove change requests

Creating Commitment Change Requests

Change Requests can be created for commitments. 

To create change request for commitments