BOQ

 

 

 

 

 

Here BOQ can be linked to the task. The quantity in BOQ can be distributed to quantity task only. Hence ensure the  required quantity task is selected in the WBS for linking a BOQ.

To link a BOQ

1.Select the tab BOQ.

2.On the window click Add.

Figure: Adding BOQ

Search BOQ window is displayed.

Figure: Search BOQ window

3.Select the required BOQ from the window and click OK.

The selected BOQ is linked to the task and is displayed in the grid.

Figure: BOQ linked to task

If the task is already assigned with a budgeted / forecasted quantity, a warning message Task contains budgeted/forecasted quantity. Do you want to assign it to the selected BOQ? is displayed. If user selects NO the operation is cancelled. If the user selects YES, budgeted or forecasted quantity is assigned to the selected BOQ.

Updating quantity allocated to task

In BOQ linked tasks the user can revise the value for  ‘Quantity Allocated to Task’.

To update quantity allocated to task

1.Double click the cell.

The cell will be editable.

Figure: Updating quantity allocated to task


 


 

 

 

 