It is a common practice in many scenarios to prepare the task list outside the system (such as in MS Excel. MS Project, Primavera etc.) Wrench uses MS Excel as a common medium through which task can be imported. Data from the planning system is exported to MS Excel, from where it is imported to Wrench. The two import options available are:

Import from Excel

Existing WBS

Import from Excel

Data entered in an MS Excel template can be imported to  WBS. When importing from excel, following options are available.

Figure: Import from Excel

Create New Tasks

Update Existing Tasks

Creating New Tasks

Task details entered in an MS Excel template is imported to WBS as new tasks. Ensure that MS Excel template is created and values are entered in the template prior to starting this operation. For more information on generating import template refer section WBS Template.

To create new tasks


Update Existing Tasks


After generating a template using the WBS Template option, task details of the same WBS can be updated using this template.

To update existing tasks

Existing WBS

This option can be used when projects are repeated. WBS of an old project can be imported to a new project and necessary changes are made to it. When the "Existing WBS" option is selected, system will display a set of Projects with matching Project types. Select the desired one from the list and the WBS of selected Project will be imported in to the current WBS.

NOTE: For carrying out this operation the target WBS has to be blank.